Laboratory Facility Elst: Dicoon
On Monday 13 June 2022, construction began on the new laboratory in Elst, to merge medical microbiology and immunology, clinical chemistry and clinical pharmacy into one building.
On Monday 13 June 2022, construction began on the new laboratory in Elst, to merge medical microbiology and immunology, clinical chemistry and clinical pharmacy into one building.
On Monday, June 13, 2022, construction began on the new laboratory in Elst, in which Rijnstate, Hospital Gelderse Vallei (ZGV) and Canisius Wilhelmina Hospital (CWZ) will merge their laboratories for medical microbiology and immunology, clinical chemistry and clinical pharmacy. The new laboratory organisation is called Dicoon. The building will be built based on the modular and circular method.
Planning
Spring 2022 Construction site prepared
June/July Piling
July / August Prefabricated foundation beams (foundation)
Summer 2022 Building steel structure and floors
Autumn/Winter 2022 Facade closed and roofing
Autumn/Winter 2022 – 2023 Interior walls and installations (finishing)
Spring 2023 Mounting and connecting medical equipment (furnishings)
Spring 2023 Test and delivery phase
Spring 2023 Landscaping
Spring / Summer 2023 Final delivery
See also the press release about this project.
Planning
Voorjaar 2022 Bouwrijp
Juni / juli Heiwerkzaamheden
Juli / augustus Prefab funderingbalken (fundering)
Zomer 2022 Opbouwen staalconstructie en vloeren
Najaar / winter 2022 Gevelsluiting en dakbedekking
Najaar / winter 2022 – 2023 Binnenwanden en Installaties (afbouw)
Voorjaar 2023 Afmonteren van medische apparatuur (inrichting)
Voorjaar 2023 Test en opleverfase
Voorjaar 2023 Terreininrichting
Voorjaar / zomer 2023 Eindoplevering
12 months
Elst
Rijnstate, Hospital Gelderse Vallei (ZGV) and Canisius Wilhelmina Hospital (CWZ)